Site update - Geotechnical works Friday 7 June 2019

As part of early environmental investigation works to support the transformation of Charles Street Square, a geotechnical survey will be undertaken by Council’s specialist consultants commencing Friday 7 June 2019. 

Work will take place between 7am-5pm and is expected to be completed in one day (subject to weather and site conditions).

While Council does not anticipate this work to be intrusive or cause disruption, please email CharlesStSquare@cityofparramatta.nsw.gov.au  or contact Council’s Charles Street Square project team on 9806 5050 if you have any further questions or concerns. 

Geotechnical works

This work will involve drilling small boreholes (around 10cm in diameter), to a depth of up to six metres in three locations across the site. Testing will require the use of a range of equipment including a ute-mounted auger.

For safety, an area around each borehole will be closed to the public, with staff directing pedestrians around the test sites as required. Once the borehole has been reinstated, capped and the area certified for safe use, the test site will be reopened. 

Who can I speak with and where can I get more information or accessible information?

Council is committed to making sure everyone can access the information they need in a format that is right for them.

If you would like to be added to the Charles Street Square contact list to receive updates, need more information or information supplied in another language or format, please email CharlesStSquare@cityofparramatta.nsw.gov.au  or contact Council’s Charles Street Square project team on 9806 5050.

May 2019

As part of early environmental investigation works to support the transformation of Charles Street Square, a geotechnical survey will be undertaken by Council’s specialist consultants commencing Tuesday 21 May 2019. 

Work will take place between 7am-5pm, weekdays (Monday to Friday only). Subject to weather and site conditions, work is expected to be completed within two days. 

Geotechnical works program

This geotechnical work will involve drilling small boreholes (around 10cm in diameter), to a depth of up to six metres in 14 locations across the site. Testing will require the use of a range of equipment including a ute-mounted auger.

For safety, an area around each borehole will be closed to the public, with staff directing pedestrians around the test sites as required. Once the borehole has been reinstated, capped and the area certified for safe use, the test site will be reopened.  

Who can I speak with and where can I get more information or accessible information?

While Council does not anticipate this work to be intrusive or cause disruption, please contact Council’s Charles Street Square project team if you have any further questions or concerns.  

Council is committed to making sure everyone can access the information they need in a format that is right for them. 

If you would like to be added to the Charles Street Square contact list to receive updates, need more information or information supplied in another language or format, please email CharlesStSquare@cityofparramatta.nsw.gov.au  or contact Council’s Charles Street Square project team on 9806 5050. 


February 2019

From March 2019, City of Parramatta and its consultants will begin early site investigations and environmental studies in and around Charles Street Square.

While Council does not expect any of this preliminary work to be intrusive or cause disruption to business operations or residents, if you would like more information on planned early site works, please contact the project team.